Project management aib and crashing and earned value

Deadline 6 PM Friday September 27, 2013

 

10 Project Management Questions with sub-questions under each question.  A word document is provided with all questions and directions.

 

 

Problem 1

The following data were obtained from a project to create a new portable electronic.

 

Activity           Duration         Predecessors 

A                     5 Days            

B                     6 Days           

C                     8 Days           

D                     4 Days             A, B

E                      3 Days             C

F                      5 Days             D

G                     5 Days             E, F

H                     9 Days             D

I                       12 Days           G

 

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

 

a)      What is the Scheduled Completion of the Project?

 

b)      What is the Critical Path of the Project?

 

c)      What is the ES for Activity D?

 

d)     What is the LS for Activity G?

 

e)      What is the EF for Activity B?

 

f)       What is the LF for Activity H?

 

g)      What is the float for Activity I?

 

Problem 2

 

The following data were obtained from a project to build a pressure vessel:

 

Activity           Duration         Predecessors 

A                     6 weeks                                          

B                     6 weeks                                          

C                     5 weeks           B                                

D                     4 weeks           A, C                           

E                      5 weeks           B                                

F                      7 weeks           D, E, G                       

G                     4 weeks           B

H                     8 weeks           F

I                       5 weeks           G

J                       3 week            I

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

 

a)      Calculate the scheduled completion time.

 

 

b)      Identify the critical path

 

 

c)      What is the slack time (float) for activity A?

 

 

d)     What is the slack time (float) for activity D?

 

 

e) What is the slack time (float) for activity E?

 

 

f) What is the slack time (float) for activity G?

Problem 3

 

The following data were obtained from a project to design a new software package:

 

Activity           Duration         Predecessors 

A                     5 Days                                           

B                     8 Days                                           

C                     6 Days             A                                

D                     4 Days            C, B                            

E                      5 Days            A                                

F                      4 Days            D, E, G                                   

G                     4 Days            B, C

H                     3 Day              G

 

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

 

a)      Calculate the scheduled completion time.

 

 

b)      Identify the critical path(s)

 

 

c)      What is the slack time (float) for activity B?

 

 

 

d)     What is the slack time (float) for activity D?

 

 

e) What is the slack time (float) for activity E?

 

 

f) What is the slack time (float) for activity G?

 

Problem 4

 

The following data were obtained from an in-house MIS project:

 

Activity           Duration         Predecessors 

A                     5 Days                                           

B                     8 Days                                           

C                     5 Days            A                                

D                     4 Days            B

E                      5 Days            B                                

F                      3 Day              C, D               

G                     7 Days            C, D

H                     6 Days            E, F, G

I                       9 Days            E, F

 

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

 

a)      Calculate the scheduled completion time.

 

 

b)      Identify the critical path

 

 

c)      What is the slack time (float) for activity A?

 

 

d)     What is the slack time (float) for activity D?

 

 

e)      What is the slack time (float) for activity E?

 

 

f)       What is the slack time (float) for activity F?

 

 

 

 

 

PROBLEM 5

Use the network diagram below and the additional information provided to answer the corresponding questions.

Crashing network 1

a) Give the crash cost per day per activity.

 

 

 

b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? What is the cost impact of crashing these activities?

 

 

 

c) Find the new budget (or cost of the project).

 

 

PROBLEM 6   Use the network diagram below and the additional information provided to answer the corresponding questions.  Crashing network 2         

a) Give the crash cost per day per activity.

 

 

 

b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? What is the cost impact of crashing these activities?

 

PROBLEM 7

Month

AC

PV

EV

22

$540

$523

$535

 

a)         Calculate the cost variance (CV).

 

 

b)         Is the CV over or under budget?

 

 

c)         Calculate the schedule variance (SV).

 

 

d)         Is the SV ahead of or behind schedule?

 

 

PROBLEM 8

 

a)         Calculate the cost performance index (CPI).

 

 

b)         Is the project cost efficient or not efficient?

 

 

c)         Calculate the schedule performance index (SPI).

 

 

d)         Is the schedule efficient or not efficient?

 

 

 

PROBLEM 9 [8 points]

 

a)         Calculate the cost variance (CV).

 

 

b)         Calculate the cost performance index (CPI).

 

 

c)         Calculate the schedule variance (SV).

 

 

d)         Calculate the schedule performance index (SPI).

 

e)         Given these data, what should a project manager do with respect to this project?

 

 

PROBLEM 10

 

 

a)         Calculate the cost variance (CV).

 

 

b)         Calculate the cost performance index (CPI).

 

 

c)         Calculate the schedule variance (SV).

 

 

d)         Calculate the schedule performance index (SPI).

 

 

e)         Explain the project performance in terms of efficiency, budget, and schedule. What should the project manager do for the project?

Get 20% Discount on This Paper
Pages (550 words)
Approximate price: -

Try it now!

Get 20% Discount on This Paper

We'll send you the first draft for approval by at
Total price:
$0.00

How it works?

Follow these simple steps to get your paper done

Place your order

Fill in the order form and provide all details of your assignment.

Proceed with the payment

Choose the payment system that suits you most.

Receive the final file

Once your paper is ready, we will email it to you.

Our Services

Custom Writings Help is a Quality-Oriented Company in Online Writing as a result of hiring exceptional professionals to execute clients' tasks.

Essays

Research Papers

At Custom Writings Help,We understand the struggle of research paper writing, and that is why at Custom WritingS Help, we are all out to help you. We pride ourselves on having a team of clinical writers. The stringent and rigorous vetting process ensures that only the 'BEST' Writers are chosen for the job. We have highly qualified Ph.D. and MA writers working with us; we equally offer these experienced writers specific bonuses and incentives to make them deliver highly original, unique, and informative content at reasonably low prices.

Admissions

Thesis Writing Service

Worlwide, Many Masters Students are struggling with Thesis Completion. A thesis is likely to be the longest and most challenging piece of work a student has ever completed. However, unlike essays and other assignments, a student can pick a particular interest topic and work on their initiative. Fortunately, we are there for you. At Custom Writings Help, you are assured of an authentic, imaginative, informative, linguistically great, and advantageous thesis that adheres to all your needs. So, why continue considering different writers when you have discovered the best in the field?

Editing

Custom Papers

Not a single student can avoid writing custom papers. However, a total lack of experience, skills, and time makes it very hard to produce a superb writing piece. Therefore, if you are seeking professional help, turn to us. Our specialized and experienced writers compose a variety of model papers, including custom essays, college term papers, research papers, book reports, MBA essays, executive summaries, dissertations, Ph.D. theses, admission essays, and research proposals for college and university students at any level.

Coursework

Essay Writing

Most of the students disregard the critical principles of essay writing and compose papers below sensible guidelines. Therefore, with Custom Writings Help, one should not worry about his/her essay. Our Writers compose informative and engaging content on all complexities and topics. We write meaningful and smart essays while prioritizing all aspects that bring about a good grade, such as impeccable grammar, proper structure, zero-plagiarism, and conformance to guidelines.

Coursework

Coourse Work Writing

Don't let the seemingly never-ending onslaught of writing assignments get you down. If you are looking where to get course work assistance online, the writers at Custom Writings Help are here to assist you with all of your writing needs. We undertake to unique delivery of papers that meet the professor's requirements. The content is proofread, edited, and checked plagiarism before submission to customers. No matter how big or small your work is, we will deliver on time. Try US Now! !

Coursework

Dissertation Writing Service

High-Quality Dissertation Writing Services are rare. They require Ph.D. academicians – not easily found. However, are an exception. The years, time, and resources we have invested in the dissertation world has given us a competitive advantage over others. Choose to come to Custom Writings Help; You will find perfect Ph.D. consultants who have written hundreds of dissertations theses ready to help you. Let our dissertation-writing services help you craft your dissertation, for you are assured we will give you the results.