Proj 592 all quizzes – week 3 and week 6

PROJ 592 Project Cost and Schedule Control – DeVry

PROJ 592 Week 3 Quiz (Version 1)

1. Question : (TCO B) Three-point estimate: The SuperFlyer Corporation is developing a revolutionary flying disc. The new toy can fly straight over a great distance, which is exciting by itself. However, this disc will also return to the owner in response to their voice! Because this is an advance over anything that this company has done before, estimating the amount and cost of the hi-tech materials are difficult. The project manager recommends using a range estimating process to develop an estimate. The values below are submitted by the project team. Current estimates for cost of material are as follows:
3. Question : (TCO B) You have been requested to provide a contingency estimate for a project involving the manufacturing of a new television. You are provided with the following component and labor estimates, together with the type of estimate:………………………..
4. Question : (TCO A) We are now in week 3 and have only discussed the plan. It is as if we will never get to work and make this project happen. Why are we taking so much time to develop the project plan, and how does that fit with monitoring and control? For full credit you must provide specific reasons and justifications, not just generalities.
5. Question : (TCO A) An environmental consulting firm has been hired to clean up contaminated groundwater beneath the site of a former chemical factory. The clean-up design process consists of evaluating several  alternatives, preparing a conceptual design for the most appropriate alternative, evaluating the conceptual design by performing a small scale pilot test on site, and, based on the results of the pilot test, preparing a final design. Installation of the clean-up system will be performed by subcontractors under the supervision of the consultant. 

PROJ 592 Week 3 Quiz (Version 2)

1. Question : (TCO B) Three-point estimate: The SuperFlyer Corporation is developing a revolutionary flying disc. The new toy can fly straight over a great distance, which is exciting by itself. However, this disc will also return to the owner in response to their voice! Because this is an advance over anything that this company has done before, estimating the amount and cost of the hi-tech materials are difficult. The project manager recommends using a range estimating process to develop an estimate. The values below are submitted by the project team. Current estimates for cost of material are as follows:
2. Question : (TCO A) Single-project budgeting must fit into the overall budgeting process of the organization and the company as a whole. As a project manager for one of your company’s projects, you have been asked to provide a brief description of the top-down approach to the budgeting process. Explain the three basic steps in the top-down budgeting approach by identifying the organizational level (Upper Management, Functional Management, and Project Management) and type of budget prepared at each step. For each type of budget, explain why it is used at its level.
3. Question : (TCO B) You have been requested to provide a contingency estimate for a project involving the manufacturing of a new television. You are provided with the following component and labor estimates, together with the type of estimate:………………
4. Question : (TCO A) We have discussed the project plan and are taking considerable time developing processes for creating it. This seems to be in conflict with the description of the course, which is Monitoring and Control. Why are we taking so much time to develop the project plan, and how does it fit with monitoring and control? For full credit you must provide specific reasons and justifications and not just generalities.
5. Question : (TCO A) A consumer electronics firm is planning an expansion into Milwaukee. Generally, the firm prefers to remodel large existing tenant spaces to suit their needs. After a site is selected from several…………….

PROJ 592 Week 3 Quiz (Version 3)

1. Question : (TCO B) Three-point estimate: The SuperFlyer Corporation is developing a revolutionary flying disc. The new toy can fly straight over a great distance, which is exciting by itself. However, this disc will also return to the owner in response to their voice! Because this is an advance over anything that this company has done before, estimating the amount and cost of the hi-tech materials are difficult. The project manager recommends using a range estimating process to develop an estimate. The values below are submitted by the project team. Current estimates for cost of material are as follows:
2. Question : (TCO A) Your manager has asked you as a project manager, “How does the Bottom-Up budgeting process work? I hear the terms bottom up and top down.” Explain the 4 basic steps in the bottom-up budgeting approach by identifying the organizational level (Upper Management, Functional Management, and Project Management) and type of budget prepared at each step. For each type of budget, explain why it is used at this level.
3. Question : (TCO B) You have been requested to provide a contingency estimate for a project involving the manufacturing of a new television. You are provided with the following component and labor estimates, together with the type of estimate:
4. Question : (TCO A) Our company has a limited time to complete our project to develop a new product. We have been assigned as the project manager and are in the process of developing a project plan. The executives are impatient with us and are “encouraging” us to move on and get started on the “actual work.” Why are we taking so much time to develop the project plan, and how does that fit with monitoring and control? For full credit you must provide specific reasons and justifications, not just generalities.
5. Question : (TCO A) An environmental consulting firm has been hired to clean up contaminated groundwater beneath the site of a former chemical factory. The clean-up design process consists of evaluating several alternatives, preparing a conceptual design for the most appropriate alternative, evaluating the conceptual design by performing a small scale pilot test on site, and, based on the results of the pilot test, preparing a final design………….

PROJ 592 Week 6 (Version 1)

1. Question : (TCO B) Crashing Problem Using the network below and the additional information provided, find: (a) The crash cost per day per activity? (b) Which activities should be crashed to meet a project deadline of 12 days at minimum cost? (c) What is the extra cost to crash the project? Activity Normal Time Crash Time Normal Cost Crash Cost A 5 3 $300 $600 B 3 2 $250 $450 C 6 4 $400 $500 D 5 3 $150 $400
2. Question : (TCO F) We have discussed at length the Earned Value Management process. I am sure all of you have used the traditional process of assessing projects where we compare actual dollars spent to the amount we had planned to spend. This was quick and easy, but it has its shortcomings, and the Earned Value Management process is said to be better. (a) Why is this traditional approach different from using earned value when assessing project performance? (b) Describe the EVM process used to determine how far our project is ahead of or behind schedule.
3. Question : (TCO E) The following information is extracted from a project to develop a state of the art alternative power energy storage device:
Activity Duration Predecessors Resources A 4 days — 1 Research Engineer B 3 days A 1 Marketing Specialist C 5 days A 1 Design Engineer D 3 days A 1 Design Engineer E 3 days B 1 Prototype Builder F 2 days D 1 Test Engineer The Owner has stipulated that in order to provide continuity throughout the project, the same individual must handle all activities under his or her discipline. Activities on this project cannot be split. (a) Identify any resource conflicts in the above project. State the activities involved, the time frame of the conflict(s), which resources(s) are involved, and the quantity required. (b) Given the owner’s stipulation regarding project continuity, and the need to minimize project duration, how can this conflict be resolved? What will be the effect on the project duration?
4. Question : (TCO F) The following data were obtained from an Information Systems project to upgrade and expand a Local Area Network: Activity Duration Predecessors Task Budget A 3 Days — $4,920 B 6 Days — $7,680 C 3 Days A $15,140 D 2 Days B $4,980 E 3 Days B $5,630 F 2 Days C, D $2,270 At the end of Day 7, the status of the project is as follows: Activity % Complete Actual Cost
A 100% $4,200 B 100% $8,740 C 100% $18,250 D 55% $2,600 E 10% $560 F 0% $0 (a) Calculate the Cost and Schedule Variances and Indexes for tasks A, B, C, D, and E. (b) As project manager, write a brief summary of the status of the project at this time
5. Question : (TCO E) We have all been associated with projects with resource problems. As a project manager, you will be responsible for resolving these problems. Remember, resources are human and otherwise. If you can name it, it may be a resource. (a) When there are not enough resources available to fill all the needs in the project plan, what are some specific remedies a project manager can take to complete the project. How does each of these affect the project plan and performance? (b) Describe 5 of the many benefits to resource leveling.

PROJ 592 Week 6 (Version 2)

1. Question : (TCO B) Crashing Problem Using the network below and the additional information provided, find: (a) The crash cost per day per activity. (b) Which activities should be crashed to meet a project deadline of 12 days at minimum cost? (c) What is the extra cost to crash the project? Activity Normal Time Crash Time Normal Cost Crash Cost A 5 3 $300 $350 B 3 2 $250 $325 C 6 4 $400 $700 D 5 3 $150 $200
2. Question : (TCO F) We have discussed at length the Earned Value Management process. I am sure all of you have used the traditional process of assessing projects where we compare actual dollars spent to the amount we had planned to spend. This was quick and easy, but it has its shortcomings, and the Earned Value Management process is said to be better. (a) Why is this traditional approach different from using earned value when assessing project performance? (b) What are some of the basic requirements for the project plan in order for EVM to be able to work?
3. Question : (TCO E) The following information is extracted from a project to develop a state of the art alternative power energy storage device: Activity Duration Predecessors Resources A 4 days — 1 Research Engineer B 3 days A 1 Test Engineer C 5 days A 1 Design Engineer D 2 days A 1 Marketing Specialist E 3 days B 1 Prototype Builder F 4 days D 1 Test Engineer The Owner has stipulated that in order to provide continuity throughout the project, the same individual must handle all activities under his or her discipline. Activities on this project cannot be split. (a) Identify any resource conflicts in the above project. State the activities involved, the time frame of the conflict(s), which resources(s) are involved, and the quantity required. (b) Given the owner’s stipulation regarding project continuity and the need to minimize project duration, how can this conflict be resolved? What will be the effect on the project duration?
4. Question : (TCO F) The following data were obtained from an Information Systems project to upgrade and expand a Local Area Network: Activity Duration Predecessors Task Budget A 3 Days — $4,920 B 6 Days — $7,680 C 3 Days A $15,140 D 2 Days B $4,980 E 3 Days B $5,630 F 2 Days C, D $2,270 At the end of Day 7, the status of the project is as follows: Activity % Complete Actual Cost A 100% $4,200 B 100% $8,740 C 100% $18,250 D 55% $2,600 E 10% $560 F 0% $0 (a) Calculate the Cost and Schedule Variances and Indexes for tasks A, B, C, D, and E. (b) As project manager, write a brief summary of the status of the project at this time
5. Question : (TCO E) We have discussed resource allocation and resource leveling and the purpose and benefits of each. We have all been associated with projects with resource issues. As project managers, we are responsible for resolving these issues. Remember, resources are human, capital, monetary, and otherwise. If you can name it, it may be a resource. (a) Define resource allocation and resource leveling and describe the difference between them. (b) When there are not enough resources available to fill all the needs in the project plan, what are some specific remedies a project manager can take to complete the project? How does each of these affect the project plan and performance?

PROJ 592 Week 6 (Version 3)

1. Question : (TCO B) Crashing Problem Using the network below and the additional information provided, find: (a) The crash cost per day per activity. (b) Which activities should be crashed to meet a project deadline of 12 days at minimum cost? (c) What is the extra cost to crash the project?
Activity Normal Time Crash Time Normal Cost Crash Cost A 5 3 $300 $350 B 3 2 $250 $325 C 6 4 $400 $700 D 5 3 $150 $200
2. Question : (TCO F) We have discussed at length the Earned Value Management process. I am sure all of you have used the traditional process of assessing projects where we compare actual dollars spent to the amount we had planned to spend. This was quick and easy, but it has its shortcomings, and the Earned Value Management process is said to be better. (a) Why is this traditional approach different from using earned value when assessing project performance? (b) What are some of the basic requirements for the project plan in order for EVM to be able to work?
3. Question : (TCO E) The following information is extracted from a project to develop a state of the art alternative power energy storage device: Activity Duration Predecessors Resources A 4 days — 1 Research Engineer B 3 days A 1 Marketing Specialist C 5 days A 1 Design Engineer D 3 days A 1 Design Engineer E 3 days B 1 Prototype Builder F 2 days D 1 Test Engineer The Owner has stipulated that in order to provide continuity throughout the project, the same individual must handle all activities under his or her discipline. Activities on this project cannot be split. (a) Identify any resource conflicts in the above project. State the activities involved, the time frame of the conflict(s), which resources(s) are involved, and the quantity required. (b) Given the owner’s stipulation regarding project continuity, and the need to minimize project duration, how can this conflict be resolved? What will be the effect on the project duration?
4. Question : (TCO F) The following data were obtained from an Information Systems project to upgrade and expand a Local Area Network: Activity Duration Predecessors Task Budget A 3 Days — $4,920 B 6 Days — $7,680 C 3 Days A $15,140 D 2 Days B $4,980 E 3 Days B $5,630 F 2 Days C, D $2,270 At the end of Day 7, the status of the project is as follows:
Activity % Complete Actual Cost A 100% $4,200 B 100% $8,740 C 100% $18,250 D 55% $2,600 E 10% $560 F 0% $0 (a) Calculate the Cost and Schedule Variances and Indexes for tasks A, B, C, D, and E. (b) As project manager, write a brief summary of the status of the project at this time
5. Question : (TCO E) We have discussed resource allocation and resource leveling and the purpose and benefits of each. We have all been associated with projects with resource issues. As project managers, we are responsible for resolving these issues. Remember, resources are human, capital, monetary, and otherwise. If you can name it, it may be a resource. (a) Define resource allocation and resource leveling and describe the difference between them. (b) Describe 5 of the many benefits to resource leveling. Format your answer in sections in accordance with the parts of the question above.

Get 20% Discount on This Paper
Pages (550 words)
Approximate price: -

Try it now!

Get 20% Discount on This Paper

We'll send you the first draft for approval by at
Total price:
$0.00

How it works?

Follow these simple steps to get your paper done

Place your order

Fill in the order form and provide all details of your assignment.

Proceed with the payment

Choose the payment system that suits you most.

Receive the final file

Once your paper is ready, we will email it to you.

Our Services

Custom Writings Help is a Quality-Oriented Company in Online Writing as a result of hiring exceptional professionals to execute clients' tasks.

Essays

Research Papers

At Custom Writings Help,We understand the struggle of research paper writing, and that is why at Custom WritingS Help, we are all out to help you. We pride ourselves on having a team of clinical writers. The stringent and rigorous vetting process ensures that only the 'BEST' Writers are chosen for the job. We have highly qualified Ph.D. and MA writers working with us; we equally offer these experienced writers specific bonuses and incentives to make them deliver highly original, unique, and informative content at reasonably low prices.

Admissions

Thesis Writing Service

Worlwide, Many Masters Students are struggling with Thesis Completion. A thesis is likely to be the longest and most challenging piece of work a student has ever completed. However, unlike essays and other assignments, a student can pick a particular interest topic and work on their initiative. Fortunately, we are there for you. At Custom Writings Help, you are assured of an authentic, imaginative, informative, linguistically great, and advantageous thesis that adheres to all your needs. So, why continue considering different writers when you have discovered the best in the field?

Editing

Custom Papers

Not a single student can avoid writing custom papers. However, a total lack of experience, skills, and time makes it very hard to produce a superb writing piece. Therefore, if you are seeking professional help, turn to us. Our specialized and experienced writers compose a variety of model papers, including custom essays, college term papers, research papers, book reports, MBA essays, executive summaries, dissertations, Ph.D. theses, admission essays, and research proposals for college and university students at any level.

Coursework

Essay Writing

Most of the students disregard the critical principles of essay writing and compose papers below sensible guidelines. Therefore, with Custom Writings Help, one should not worry about his/her essay. Our Writers compose informative and engaging content on all complexities and topics. We write meaningful and smart essays while prioritizing all aspects that bring about a good grade, such as impeccable grammar, proper structure, zero-plagiarism, and conformance to guidelines.

Coursework

Coourse Work Writing

Don't let the seemingly never-ending onslaught of writing assignments get you down. If you are looking where to get course work assistance online, the writers at Custom Writings Help are here to assist you with all of your writing needs. We undertake to unique delivery of papers that meet the professor's requirements. The content is proofread, edited, and checked plagiarism before submission to customers. No matter how big or small your work is, we will deliver on time. Try US Now! !

Coursework

Dissertation Writing Service

High-Quality Dissertation Writing Services are rare. They require Ph.D. academicians – not easily found. However, are an exception. The years, time, and resources we have invested in the dissertation world has given us a competitive advantage over others. Choose to come to Custom Writings Help; You will find perfect Ph.D. consultants who have written hundreds of dissertations theses ready to help you. Let our dissertation-writing services help you craft your dissertation, for you are assured we will give you the results.