1. All five members of a project team add 15% to their individual serial activities as a safety margin and submit their time estimates to the project manager. The manager adds the activity length estimates together and adds 10% for his personal safety margin. Then, anticipating a cut by top management, adds another 10% to his final project estimate. Much to his surprise, top management cuts 30% off his time estimate. How much of a cushion is now built into the project?
a 13%
b. 7%
c. 5%
d. -3%
2. All five members of a project team add 20% to their individual serial activities as a safety margin and submit their time estimates to the project manager. The manager adds the activity length estimates together and adds 20% for his personal safety margin. Then, anticipating a cut by top management, adds another 20% to his final project estimate. The executive level of the organization just completed a retreat where they read The One Minute Manager, Who Moved My Cheese and Critical Chain. They return from their retreat both energized and much wiser in the ways of project management. They know that everyone has been routinely adding 20% and want to scale the project back to an unpadded estimate. How much should they cut?
a. 42%
b. 60%
c. 33%
d. 27%
3. The student syndrome of wasting extra safety time can be described as ______________.
a. lack of motivation
b. procrastination
c. failure to communicate
d. lack of comprehension
4. Which of the following statements about CCPM activity networks is correct?
a. Project workers are more likely to meet a deadline for their activity than miss it.
b. There are no milestones in the CCPM activity network.
c. Project workers are more likely to miss a deadline for their activity than meet it.
d. There is no project delivery deadline in the CCPM activity network.
5. Subcontractor deliveries are difficult to schedule with the critical chain project methodology because ____________.
a. the project manager cannot force subcontractors to use this project management approach
b. the feeder buffers for a subcontractor are as much as 50% shorter than for an employee or internal team
c. subcontractors routinely operate according to calendar delivery dates
d. the corporate culture of “no blame” does not naturally extend to subcontractors
6. The buffers supplied to noncritical paths in critical chain project management are called _____________ buffers.
a. slack
b. drum
c. rope
d. feeder
7. The amounts of individual resources that a schedule requires during a specific time period is referred to as the resource’s ______________.
a. loading
b. capacity
c. constraint
d. drag
8. A resource loading form is also known as a(n) ______________.
a. load schedule
b. resource usage calendar
c. activity resource schedule
d. network resource profile
9. A resource loading chart displays the amount of ______________.
a. time needed as a function of resource limits
b. resources required as a function of time
c. time needed as a function of money
d. resources needed as a function of money
10. Splitting activities refers to _____________.
a. assigning the work to two or more workers
b. assigning the work to two or more days
c. starting an activity, interrupting it to use a resource elsewhere and then returning to work on the activity
d. breaking each noncritical activity into two or more components and subdividing the resources they use by a similar divisor
11. The Minimum Late Finish Time rule stipulates that the _____________.
a. earliest late finishers are scheduled last
b. latest early finishers are scheduled first
c. earliest late finishers are scheduled first
d. latest late finishers are scheduled first
12. Mathematical programming is sometimes used to generate optimal solutions to resource constrained problems in a multi-project setting but suffers from _____________.
a. an inability to model project and activity due dates
b. resource substitution
c. resource constraints
d. problem complexity
13. In earned value management, schedule variance is defined as the difference between the _____________.
a. earned value and the actual cost
b. earned value and the planned value
c. actual cost and the planned value
d. cost and schedule performance indices multiplied by the budgeted cost at completion
14. The budget variance is calculated as _____________.
a. earned value minus planned value
b. planned value minus actual cost
c. earned value minus actual cost
d. cost minus planned value
15. In earned value management analysis, the cumulative amount of the budget becomes the _____________.
a. planned value
b. scheduled value
c. cost basis
d. cost driver
16. The project baseline is established by combining data from the _____________.
a. work breakdown structure and the project budget
b. time-phased project budget and the PERT chart
c. S-curve and the project budget
d. time-phased project budget and the work breakdown structure
17. Take the factors considered by earned value analysis and subtract those considered by project S-curves. The factor(s) you have remaining are _____________.
a. performance and cost
b. cost and schedule
c. time
d. performance
18. Knowing the correct steps to take once problems develop is a function of a team’s ___________ ability.
a. communication
b. client acceptance
c. troubleshooting
d. technical task
19. Earned value management is also known as _____________.
a. the golden triangle method (GTM)
b. the achieved value method (AVM)
c. the program evaluation and review method (PERM)
d. earned value analysis (EVA)
20. All projects are unique _____________.
a. therefore all project management circumstances are equally unique
b. so knowledge cannot be transferred
c. but they may have several common points
d. so knowledge should not be transferred to avoid bias in future projects
21. Lessons learned analysis is best described as a(n) ______________ process.
a. bookkeeping
b. personnel reassignment
c. pressure relief
d. organizational learning
22. Which of these is not a consequence of a natural process for project closeout?
a. Team members suffer a natural let-down and are de-motivated to participate in future projects.
b. Managers can create a database of lessons learned analyses.
c. Closeout can serve as an important source of information for team members.
d. Structure for a systematic and complete project shut-down arises.
23. Which of these statements about early termination decisions is best?
a. The decision to pull the plug is usually clear-cut.
b. A project’s viability is usually a purely internal issue.
c. Projects that can fulfill a useful purpose in the marketplace are not killed.
d. External reasons, such as a change in the organizations environment, are often the reasons for project termination.
24. A mainframe computer company decided to enter the personal computer market with its Floridian Project, but subsequently decided to leave the market to focus on the mainframe business. The decision rule that they probably applied was to get out when ____________.
a. the project no longer meets strategic fit criteria
b. deadlines continue to be missed
c. project personnel turn over too rapidly
d. technology evolves beyond the project’s scope
25. The rapid evolution of technology and the need to freeze a project’s scope can combine to render a project ____________.
a. too costly to complete
b. obsolete before it can be finished
c. a poor fit with current company strategy
d. so complex that it will take too long to complete
Try it now!
How it works?
Follow these simple steps to get your paper done
Place your order
Fill in the order form and provide all details of your assignment.
Proceed with the payment
Choose the payment system that suits you most.
Receive the final file
Once your paper is ready, we will email it to you.
Our Services
Custom Writings Help is a Quality-Oriented Company in Online Writing as a result of hiring exceptional professionals to execute clients' tasks.
Essays
At Custom Writings Help,We understand the struggle of research paper writing, and that is why at Custom WritingS Help, we are all out to help you. We pride ourselves on having a team of clinical writers. The stringent and rigorous vetting process ensures that only the 'BEST' Writers are chosen for the job. We have highly qualified Ph.D. and MA writers working with us; we equally offer these experienced writers specific bonuses and incentives to make them deliver highly original, unique, and informative content at reasonably low prices.
Admissions
Thesis Writing Service
Worlwide, Many Masters Students are struggling with Thesis Completion. A thesis is likely to be the longest and most challenging piece of work a student has ever completed. However, unlike essays and other assignments, a student can pick a particular interest topic and work on their initiative. Fortunately, we are there for you. At Custom Writings Help, you are assured of an authentic, imaginative, informative, linguistically great, and advantageous thesis that adheres to all your needs. So, why continue considering different writers when you have discovered the best in the field?
Editing
Custom Papers
Not a single student can avoid writing custom papers. However, a total lack of experience, skills, and time makes it very hard to produce a superb writing piece. Therefore, if you are seeking professional help, turn to us. Our specialized and experienced writers compose a variety of model papers, including custom essays, college term papers, research papers, book reports, MBA essays, executive summaries, dissertations, Ph.D. theses, admission essays, and research proposals for college and university students at any level.
Coursework
Essay Writing
Most of the students disregard the critical principles of essay writing and compose papers below sensible guidelines. Therefore, with Custom Writings Help, one should not worry about his/her essay. Our Writers compose informative and engaging content on all complexities and topics. We write meaningful and smart essays while prioritizing all aspects that bring about a good grade, such as impeccable grammar, proper structure, zero-plagiarism, and conformance to guidelines.
Coursework
Coourse Work Writing
Don't let the seemingly never-ending onslaught of writing assignments get you down. If you are looking where to get course work assistance online, the writers at Custom Writings Help are here to assist you with all of your writing needs. We undertake to unique delivery of papers that meet the professor's requirements. The content is proofread, edited, and checked plagiarism before submission to customers. No matter how big or small your work is, we will deliver on time. Try US Now! !
Coursework
Dissertation Writing Service
High-Quality Dissertation Writing Services are rare. They require Ph.D. academicians – not easily found. However, are an exception. The years, time, and resources we have invested in the dissertation world has given us a competitive advantage over others. Choose to come to Custom Writings Help; You will find perfect Ph.D. consultants who have written hundreds of dissertations theses ready to help you. Let our dissertation-writing services help you craft your dissertation, for you are assured we will give you the results.